Ørsted Kalundborg CCS

SLB Capturi is delivering a large-scale carbon capture project to Ørsted, a global leader in renewable energy, for its Ørsted Kalundborg Hub in Denmark. As the carbon capture provider, SLB Capturi will deliver five Just Catch™ units, additional equipment such as liquefaction systems and temporary CO₂ storage and on-/offloading facilities. The carbon capture facilities will be delivered to Ørsted’s wood chip-fired Asnæs Power Station and the Avedøre Power Station’s straw-fired boiler and combined will have an installed design capture capacity of 500,000 tonnes of CO₂ per year. The product CO₂ will be of Northern Lights storage quality. The CO₂ will be transported to a new CO₂- hub in Kalundborg, Denmark, and shipped to Norway for offshore storage. The plants are planned for delivery in Q4 2025 and are currently in construction.

  • Year: 2023 – ongoing
  • CO₂ capture capacity: 500.000 TPA
Subscribe to our newsletter